Downtown BendTop story
Franklin Avenue underpass will reopen to drivers Nov. 20 for the holidays
Franklin Avenue's underpass will reopen Nov. 20 and close again in January
- Sept.In early September, Franklin Avenue closed to vehicles for downtown construction.
- Nov. 20The underpass reopens to traffic at the end of the day.
- Jan. 2027The holiday reopening ends, according to the city's notice.
- May 2027The project's completion is scheduled for Memorial Day weekend.
Sources: Central Oregon Daily, KTVZ
If you've been dodging downtown Bend, the Franklin Avenue underpass reopens to traffic at the end of the day Fri., Nov. 20 for the holiday season. Crews are a week ahead of schedule and paving now.
Roughly 14,000 drivers a day used Franklin before it closed. Ivan Johnson, who owns The Lion's Den Barbershop at Hill Street and Franklin Avenue, says foot traffic has suffered: "if you're not driving it, you can't see it."
14,000drivers a day used Franklin Avenue before the closure
Roughly that many drove the street daily until construction closed it in early September.
Source: Central Oregon Daily
- Reopens: end of day Fri., Nov. 20
- Closes again: Jan. 3, 2027, per the city's notice
- Other work: utility work expected along Hill Street
- Finish line: Memorial Day weekend 2027
Senior project engineer Todd Johnson says the Downtown Bend Business Association asked for the reopening, "supporting small businesses, providing another road and access into shopping, restaurants, etc." The city's notice says the reopening runs through Jan. 3, while Central Oregon Daily reports Jan. 4. We'd plan around the earlier date.